Setup routings using Machine centers

Hi,

I’m trying to setup routings using Machine centers. This is how the scene is:

Work Group: Prod

Work Center: Sliters

Machine Centers: MC01 (Machine 1), MC02 (Machine 2), MC03 (Machine 3), MC04 (Machine 4)

Now the problem is all the machines (1,2,3,4) can do the same jobs. If

Suppose for product A I setup the routing (RT01) by using MC01 & my production team create a production Order for Item A and wherehouse team wants to produce that item on machine 3 (MC03), then… this creates the problem to track the right thing, to track everything correctly we needs to change the routing from MC01 to MC03 & then post to track everything under right Machine center.

We are also trying to use Production schedule (Gantt Chart). Ques: If we drag the planned production order from one machine center to another will it change anything at the back to.

I don’t know if I explained it clearly or not, if you need more information plz let me know

Thanks