Sheduling job with MRP

Hi all, I have a customer who needs to know on which WC , job will be done. Actually an item can be produced at different WC and the planner needs to assign the production order to multiple WC. I know that in Navision only one routing is attached to the Item, but the planner needs to assign jobs i.e: 100 pcs to WC1 and 200 pcs of WC2, etc… for a paricular Production order that MRP has proposed. Does anybody knows if there is a way to handle that situation without doing customisation??? Thanks RF

Look at www.olivia-sistemas.com FCS. You must setup WC, but work with Machine centers FCS reasign planer needs. Best regards from BCN. Salut!