Route details

Hi,

I have an query with respect to route details.

I have a scenario where i need to have same operation in the route form with different setup and run time in the Rout master. For ex: I have an operation called “Inspection” which occurs multiple times during the stage of production, but the setup time will vary from one stage to other.

In the Route master, I’m able to provide the same operation multiple times, but the system does not allow to provide different setup and run time, where is in the Production Order–>Route i’m able to set different setup and runtime.

Please provide me a possible solution for this?

Regards,

Satish EC

Simple solution, create different operations, for example: Inspection1, Inspection 2, and so on.