Resources-routes-operations guidelines

Hello everybody! Can give me some main guidelines to setup the following scenario?

  1. Two semi-finished production lines A and B, some items I want just to be scheduled in A but not in B, and viceversa.

  2. Just want to have one operation in each line, but the operation has different performance in each line (100lb/hour line A and 200lb/hour line B)

  3. Based on capacity utilization and time to finished the orders the user may have to choose a 18hs/day calendar or 24hs/day

  4. would like to analyze capacity based on planned orders, not firmed orders