Rae material required for production ax 2012

Dear,

we are now implementing MS dynamics 2012, my case is that i have 3 warehouse (raw material, WIP, finished products), i want to create production order for product (fromula type) ( the warehouse in the formula lines is prodction warehouse) is there anyway to automatically move the required products for production order from raw material warehouse to the production warehouse, i tried the output orders but its not working properly unless within the same warehouse.

Can anyone advise please

Thank you

You would need to set the item coverage up with rules to transfer into the production warehouse from the RM warehouse - AX does not really do physical WIP so it depends what you are using that for. Anyway if you set the rules up hte demand on production will suggest a transfer from raw material and actionaing this you can process it into the warehouse.

Thank you for your reply in fact i wanted to find solution without using master planning, can the output order solve the problem? if we did the required setup

No, for auto replenishment of stock between warehouses you need to use planning