When Production Order is scheduled for first time, route scheduling is calculated as per requirement.
But when if it is scheduled again, the scheduled start date and time changes (Scheduled after previous job run) and when it executed 3rd time it again calculates as per requirement (As per 1st calcualtion).
What could be the issue…? Is any setup parameter missing…?
Test1: Calculated for 1st time
Oper. No. | Operation | Resource | Remain status | Start date | Start time | End date | End time |
---|---|---|---|---|---|---|---|
30 | Assembly | 1226 | Route consumption | 01-05-2016 | 00:00 | 01-05-2016 | 16:42 |
40 | Mix/Heat | 1111 | Route consumption | 01-05-2016 | 16:42 | 02-05-2016 | 01:03 |
40 | Mix/Heat | 1112 | Route consumption | 01-05-2016 | 16:42 | 02-05-2016 | 01:03 |
Test 2: Calculated for 2nd time
Oper. No. | Operation | Resource | Remain status | Start date | Start time | End date | End time | |
---|---|---|---|---|---|---|---|---|
30 | Assembly | 1226 | Route consumption | 01-05-2016 | 16:42 | 02-05-2016 | 09:24 | (Incorrect) Scheduled after end time of 1st run |
40 | Mix/Heat | 1111 | Route consumption | 02-05-2016 | 09:24 | 02-05-2016 | 17:45 | |
40 | Mix/Heat | 1112 | Route consumption | 02-05-2016 | 09:24 | 02-05-2016 | 17:45 |
Test 3: Calculated for 3rd time
Oper. No. | Operation | Resource | Remain status | Start date | Start time | End date | End time |
---|---|---|---|---|---|---|---|
30 | Assembly | 1226 | Route consumption | 01-05-2016 | 00:00 | 01-05-2016 | 16:42 |
40 | Mix/Heat | 1111 | Route consumption | 01-05-2016 | 16:42 | 02-05-2016 | 01:03 |
40 | Mix/Heat | 1112 | Route consumption | 01-05-2016 | 16:42 | 02-05-2016 | 01:03 |
When it is executed 3rd time, again it is calculated correctly as per requirement.
This cycle goes on for even and odd run.
Pls. help.