Hi,
after we click the “Refresh Production Order” button, the FPO due date change back to 12/31/2013 although we set all date to 1/3/2014. does anybody can help us to fix this issue ?
Ps. we are not use routing function now.
Thanks
Hi,
after we click the “Refresh Production Order” button, the FPO due date change back to 12/31/2013 although we set all date to 1/3/2014. does anybody can help us to fix this issue ?
Ps. we are not use routing function now.
Thanks
You need to make calculate work center do this steps
1- go to manufacture section
2-the select work center
3-planning - calender
4-from work center calender - function - calculate
5- select every work center then make in option starting date from 01-01-2014 and end date 31-12-2014 and in No select work center no then OK
Now this error will be solved
Ahmed,
Thanks, I fixed.