Hi, I’need help.
This is the scenario.
Sales Order item A 1000 pcs delivery date . 01/20/08
Relesead Production Order item A 1000 pcs with a single line routing line on a external work area (subcontractor) with end date 01/18/08.
MRP propose to do nothing because the Prd.O end before delivery date. (that is OK)
it happens oft that the subcontractor is late of one 10 day, so i’have to modify the end date of the PO to 01/28/08. (the same happpens if i’ve problem with internal work area )
When i run again the MRP, it propose to create a new PO with end date 20/01/08: as i saw in the code, MRP consider that the Released PO (with posted item ledger entries) is not rescheduleable (flexibility “none”), and because the PO end after the Sales order delivery date mrp tell me to create new PO
The problem is that if i have not the component that are necessary to make the ProdOrder item, MRP could tell me to create new Purchase order for the component…
It is not simple to realize that the new Prd order is not necessary…in particular if i have 300/400 Prod order to manage…
I can realize that the Prdo. order is not necessary id the start date is in the short period or before today…
I’ve explain my custom that is not an error; usually, if the forecast/production manager work properly, at zero-period he have the supply to meet the demand in the short period (next 3-4 week).
So the manger have to plan the long run (i.e. next month)…so If the MRP propose to release new order in the past or in the short period this mean i’ve problem with supply and demand…
Nobody meet the same problem.???
It can be considered as a MRP bug, or not.???
Somebody try to modify MRP routine in order to let MRP reschedul RProd,order even so they have posted ledger entries???
thanks
ale