How is Last direct cost in item ledger calculated

Hi,

Am using NAV 2013 R2 Version 7.1, I want to know how is last direct cost in item ledger calculated? i understand it is the last purchase price, however, in my case i see this is also appearing in the manufacturing item. if i view the capacity report, the system is using this last direct cost and calculates the actual cost.

Please help

Many thanks

Hassan

Last direct Cost was only used initially when calculating costs of purchased materials that have not been invoiced. Once the true costs are known NAV will make the necessary adjustments through Adjust Cost batch job.

NavCon

Hi Harun,

Just go to the Last Direct cost field of the page and press f1. You will see the help page of it. It will describe all you want.