WC Capacity with Shifts

Hi folks,
I have a work centre with 2 shifts, but with different numbers of staff per shift - 4 staff are available during the dayshift, and only 2 on the nightshift. The nightshift is split into the next day, so the shop calendar working days looks like this:

However, when I calculate the Work Center calendar, this is the capacity it shows me:

It’s adding capacity which doesn’t exist - using 4 resources per shift, even for the nightshift.

Any ideas on how to clean this up so we have a realistic production schedule please?

Cheers,
Hamish

You are using the Insight Works MxAPS extension, which adds the “Available Resources” to the Working Days page. I would encourage you to reach out to your partner or Insight Works for how to utilize this field.