Table Job Task "Cost Completion %" field in 2009 sp1.

Hi Expects,

I have come across a situation, i want to share this and just want to know about how can i solve this,

We have just upgraded from 2009 sp1 to NAV 2013.

In 2009 sp1 table Job Task Line, the user has used the field “Cost Completion %” to see the difference between the Usage Cost v/s Schedule Cost.

Now when i check in NAV 2013 the field no. 54, field name “Cost completion %”, in the Table Job Task is no more.

How to solve this can add a new field for the “Cost Completion%” or there is a change in the functional of COst Completion%.

Thanks

Naveen

Hi Naveen,

The Cost Completion % in NAV 2009 was used by the old WIP functionality. And although NAV 2009 had WIP functionality then it was really not very good. Therefor it was completely rewritten for NAV 2013 and the Cost Completion% and Invoiced % fields are not longer needed. So they where removed.

So I suggest that you study the new WIP functionality, as you will find it here.