Jobs & Resources Cost Posting

In Navision all costs associated with a job can be posted to only one cost account per job. What if different costs associated with a job is required to be posted to different accounts for example material cost to material account, expenses to respective G/L accounts and resource cost to labor account. Can anyone suggest some solution? [;)]

Hi, There is no way to do this in standard navision. Needs customization to achieve this functionality.

Yes, you’ll need some modification in order to achieve this. There are also add-ons available for Job costing. There’s a guy named Rick Baxter in the US that made a Navision add-on for the jobs. I don’t know if he’s still around in the Navision world. I forgot his company name as well… =(

Thanks 4 the replies