Intercompany Planning AX 2012

Hi,

I am facing this issue while working through intercompany master planning.

I create a planned order in company A through master planning which generates a planned order in company B based on inter-company vendor relation. Now the issue is the delivery date in company A is reflected as requirement date in company B which is not correct as there is a lead time for transport. I tried the sales lead time in company B to reflect the right requirement date in company B but it takes lead time from sales parameter and that is not correct as lead time changes based on customer. I tried the transport lead times to calculate it but i think transport lead times are not considered in planning. Please suggest a way out as it is very critical for supply chain.

Thanks,

Anyone???