we have a situation here. we recently migrated from 3.7 to 5.0. On the Go Live day, consultants posted dummy Item quantity and values as an opening balance in order to start with Dynamics Nav 5.0. After a month, we finalised the inventory after closing the year. Now we have correct Item Qty and Values. These Qty and Values needs to be replaced with the dummy Qty and Values posted previously as an Open Balance. The dummy opening entries are already applied with the sales transaction. The consultants are suggesting to do stck take and correct the cost from now onwards, which is practically not feasible at the moment.
Is there a way out that we can post the correct inventory balance and revalue the cost from the go live date onwards? quick reply will be highly appreciated.
once you post the any transactions then system will update the Ledger entries.
so you cannot replace that ledger entries , but u have to make adjustments to that ledger entries.
so when ti comes to your query if you have taken excess qty then use the Negative adjustment on same date.
if you have taken that less quantiy then use the postive adjusment on same date.
when it comes to Value then use the revalueation journal to adjust the cost for Opening balance.
You can fill the revaluation journal manually in the revaluation journal for that item, use “applies-to entry no” and select the positive entry to revalue for which quantity is not remaining,
then system will post that entries to Value entry and Inventory accounts will effect.
I mean to say that the subsequent sales entries are already valued with the wrong cost uploaded as an opening balance. So this valuation of the sales entries can be corrected with this revaluation process?
Yes,u will have to run adjust cost entries and post inventory cost go G/L batch jobs respectively, but ask ur accountants which period they would think they r allowed to get it posted (i mean adjustments), in the month in which u posted the opening or the current month.
BTW what costing method u have ? In any case first do this on a local copy of ur db, verify the outcome, if everything seems fine then do it on production db.
Hi, i have a problem on entering opening balance using Item Journals. WHen i try to post item journal line, it says that General Posting Setup does not exists. General Bus. Posting Group='Gen.Prod.Posting Group=RM-AWCU. I guess I have checked everything and I cant see any problem. Since when I tried to post from Purchase Invoice using the same item it works.