Dear All,
I have route for an item XXXXXXX as fallows;
operation no operation name time next operation
10 cutting 20 min 20
20 welding 40 min 30
30 painting 15 min 0
Now when i estimate the production of item XXXXXXXX for quantity 10
operation no operation name total time next operation
10 cutting 200 min 20
20 welding 400 min 30
30 painting 150 min 0
Here system shows that we need to wait for 200 min to start operation 20(welding).
But i need to start operation 20(welding) after operation 10(cutting) i.e 20 min of first item.
Here What i mean is,i need to process operations simultaneously with out wait for others.