Routing steps : change final Mat.Cons. and Time

Hi! I’d like to know if it possible, on a Production Order, and during one of the routing step nr.3 (Total Routing steps = 7), to change the forecasted Materials consumptions quantity and time length (only that routing line = 1 BOM line) really used. And after validating this routing line, then next routing line can proceed. Can this be easily updated and done? [:o] Thanks. Z

Z, You can open the production order, use the Item button, then Components option to change the Qty Per for any line which will re-calculate the Expected and Remaining Qty. As for the Routing; from the production order-Item button select Routing. Show Columns in the form to make the Schedule Manually, Starting Time and Ending Time visible. Flag Operation steps 1-3 as Manual, make the adjustments to step 3, operations 4-7 will re-schedule automatically. Good luck, BR