V3 & 4
The Resource Price is in USD, the LCY is GBP.
How or where is the Currency price used for Resources?
The Job journal is used to enter the usage (timesheets) using the Resources, these are then invoiced using the Get Job Usage. All OK for LCY priced Resources BUT I cannot see how to post entries to a Job for this resource with anything other than LCY.
The Job journal does not recognise the Currency Price so LCY prices are calculated manually at an exchange rate for the usage posting date (that can be made automatic with code unless the whole concept fails).
When invoicing the Job usage, the LCY is converted to USD at the invoice Posting Date rate.
If the invoice line is changed to reflect the quoted USD price, a line discount is created.
If the invoice line is simply entered against the Job, any difference in the exchange rate is shown as an outstanding amount when applied to the open Job ledger entries.
Am I missing the point? How do I bill the customer in USD at the quoted Resource Price in USD?