Hi All,
Is it a standard of AX, to allow approval of budget revision which would cause the remaining budget to go negative?
I have tried revising a project Budget. The original budget is 100, consumed is 60, so my remaining is 40. I revised, deducting 50 from it. The system allowed it, causing the remaining budget to go negative.
My setup in Project is
-Active Budget Control
-Disallow overrun for Costs
Am I missing any setup or this is AX standard?
Thanks in Advance!
Bella