hi,

i would like to post journals for a large selection of started short production orders, instead of manual journal posting on an ‘order by order’ basis.

thanks in advance,

“R”

HIghlight them all - select update and start, on the general tab set the picking list to “Always”, tick the post now and end flag and press OK.

thanks Adam,

i have the preflush end covered… but i would like to back flush all journal lines that were not able to be posted initially…??

cheers,

Richard

I will guess this is ad hoc and not defined back flushing, so you cannot use the flushing method on the RAF journal. Try the always, but the issue is in your process, whether you have created the line and short posted it and ended it. Basically you would need to define what you are doing, the steps taken, and then what you are trying to achieve.