Not picking earliest shipping date when pegging a production order

Hi all,

when Pegging an production Order in ax 2012 it is not always grabbing the earliest ship date, in the below PO there is a salesorder of date 1/29/2018, but it is taking next value of 2/19/2018, Can anyone help where it is going wrong and how this can be solved? from where this date is populated ? Please suggest with a solution

Thanks in advance,

Gopinath

It looks more of a functional question (that belongs to user forum). What is your expectation in developer forum?

Hi Kranthi,
I wanted to know technically from where this Requirement date value is coming and how the value is processed, it is coming from a temp table (TmpReqTransDown) but want to know how this field is processed at the back end please suggest a solution.

Thanks,
Gopinath

It is ReqTrans.ReqDate. Try looking at the cross references.