If a manufactured item(FG) has only on raw material(RM) & only one operation.
The time required for manufacturing one unit of FG is 5days & purchase leadtime
for RM is 2 days.
What should be the manufacturing lead time for FG is RM is not in stock = 5 days or 7 days.
I made a Sales Order of todays date & got a planned batch order after 7 days means AX is taking 7 Days.
Manufacturing lead time should only be the time required to process unit quantoty(Setup+run+que+move+)
of he FG & shoul not contain the RM prurchase lead time right?