I have an query with respect to Master scheduling for Planned Production Orders and Planned Purchase Orders.
Both for FG and RMs i dont have any On Hand Qty. My demand for FG items is been specified as Sales Quotations / Sales Orders.
I have a Sales Quotation as a demand for the FG Item which has the Active Routes and BOM. In the Sales Quotation i have given Scheduled Ship date / Receipt date as 06-June-2011.When I run the Master scheduling on 13-June-2011, AX generates the Planned Production Order for the FG Item and Planned Purchase order for Raw materials.
Due to Work center capacity constraints, AX suggest Planned Production orders dates as Order date - 13-Aug-2011, Delivery date - 27-Sep-2011 and Request date - 13-June-2011.
What abt the Order dates for the Raw materials? AX suggest the Order dates, Delivery date & Requested date - 13-June-2011, but in the pegging section in the reference it shows the requirement date as 13-Aug-2011.
Why the system suggesting the date as 13-Jun-2011 instead of 13-Aug-2011 for the Raw Items, because I’m going to start the Production order not before 13-Aug-2011.
Can anyone explain me abt this?? In the BOM I have not mapped any operations nos against the BOM Lines.
Awaiting for your inputs.
Regards,
Satish EC