Labor and overhead cost in AX 2012 R2

Hi,

I just want to ask. In the costing version, how I would check that the labor cost and overhead cost is allocated correctly in the route card? I want to check because my COGS in production is really high. Hope you help me understand this.

Thanks,

Kristine

Dear Kristne,

there are two ways of checking the additional applied cost.

one you can check direct from costing sheet where you define the calculation group and amount.

and second one is go to the particular bom item and in manage cost tab click for the item price and here also you can check the applied amount.

hope this will help.

On the production order itself the production posting and estimation options will also show you what was calculated and posted.