How to update time for Route Scheduling.

Hi All,

i have problem with Production job, as we look at the “ROUTE” of Scheduled job. in that form look at “SCHEDULING” tab

as shown below. here we did change at calender, and time of delivery but this time is remains 12:00 am.

any one have idea how to set/change this time. please do help asap.

Thank you,

Mehul Thacker.

The information what you are showing in the Route will be Actually Picked up from the route when production order is Estimated or Scheduled. You cannot edit the information in the Scheduling Tab - it is according to the setups made at the route attached to item.Based on those setups the system will schedule the start date , time and end date , time for operations.

If you created a new calendar - did you attached it to the work center. If not attach it to the work center.

or if you changed the existing calendar.

again update the route. and do the estimation again.

Hope you understood…

Hi Kranthi,

Yes , i cant change time on this scheduling column.

I have attached calender to workcenters.

and during scheduling as we provide date jobs getting scheduled but time is always 12:00am in any case you have mention.

You have no times against your routing. The 12.00 time comes from the planning parameters. Reschedule would alter it, but it will go back from the end time based upon the time and then define the start time. In your example it would never change.

As Adam said - Have you specified Run Time for you operations??

yes i have specified run time for both as 0.05 means 5 minute.

i have not problem whit this specific production line. even i create new production line & check route for that new production order. it will be “12:00am”

"can you tell from where it is fetching this start time for Route?"

You will get this from Work Centers/Groups and the Working Times Composed.

The start time and end time are the same, so there is no 5 minutes here!!

But working backwards it will get it from a number of places. When you schedule the order you tell it the scheduling time, failing this I believe the planned order would have looked at the planned receipt time, and then these are adjusted as Kranthi states by the working times of the work centre to get the nearest time. I suggest you start by scheduling an order and changing the time to see the impact.