Costing Sheet Setup

Hi all,

We have configured the Costing sheet with Material, Labour and Plant Overheads and specified the respective Accounts in the Costing Sheet screen along with the Financial dimension. In the Chart of Accounts we have specified the Dimension as “To be filled in”.

We have given the Financial dimension in the Production Order dimension group. We need this dimension specified in the Production Order to be mapped when the the Indirect Posting happens.

Currently the Financial dimesions is been taken from the Costing Sheet instead of the Dimension specified in the Production Order.

Is there anyway to achive this?

Regards,

Satish

The dimension tab on the indirect is used to post the dimension related to the indirect rather than the production order. If you want to change the dimension posting structure you would need to modify the routine to handle this I believe.