Changing the Delivery Method Route in the form Change Lifecycle Status ?

Hi all,

its me again. Today I took a closer look at the form “Change Lifecyle Status” in PIM > Released Products > All Products. I wonder if its possibly to change the “Delivery Method Route” in this form, without adding it to the form through the AOT ? Can someone answer this question ?

BTW I am using Dynamics AX 2012 R3.

Thanks for reading.

BR !

What is the AOT name for that form?

Hi,

the name of the form I am looking at is “EcoResProductLifeCycleStatusChange” - EcoResProductListPage. .

BR

I don’t see EcoResProductLifeCycleStatusChange from in standard.