Hi,
I want to use capability functionality for Job scheduling of resources.
I have 9 resources (Work Centres) and I have attached capability as dipping . Resources functionality is same only cycle time differes .
on route I have mentioned resource require 9 and attached capability as dipping. each resources having priority from 1 to 9 .
My requirement is if I run job scheduling system has to schedule on these 9 resources as per priority and capacity available.
Here I am getting error capacity not available or system is only scheduling on 1st priority . System only considering one resource while scheduling .
Require output : System should schedule as per priority and capacity availability to full fill demand in time.
Thanks in advance.