AX2012 Project Management and accounting add-in

Hi

I have the project management add in feature enabled on ax 2012.

I create the project quotation, define the lines and categories i need, however when i want to send and confirm the quotation, the buttons " Send" and “Confirm” are disabled. I even created the WBS just in case it was mandatory.

is there something I am missing? maybe in the module parameters?

please help.

thank you :slight_smile:

Rola

solution is to set up the Project quotation template workflow.