Hi,
I working on resource scheduling in Dynamics AX 2012. In my scenario I am scheduling 2 resources in one operation. Following are the details:
- Both resources belong to one resource group.
- On the operation I have set this resource group as resource criteria and provided quantity of 2 for the Resources.
- Operation Runtime is set to 3 hours.
Now I’m scheduling a production order having 2 quantity for finished good. I was assuming that both the quantities will be divided between the two resources, and each will be scheduled for 3 hours in parallel making 6 hours in total. But in reality both resources are scheduled for 6 hours each.
Is this the behavior which I should expect or am I doing something wrong?
Thanks