Alert / Notification All Materials Are On-Hand for Production

Some of our production groups have hundreds of open production orders. They all are waiting on other materials to either finish being made or procured.

Is there a means to mark on a production order or to be notified / alerted to when a given order’s raw materials are all available on-hand and it is ready to be produced?

(AX 2012)

There is no mark to signal start due to everything being there. If you are using planning then the dates can move and impact on what you are trying to do will be seen in planning. If you went to a production order and pressed Inquiries and Explosion this would show you issues (Setup button and overlay a graphic).