Works order moving across multiple warehouses

Currently on AX2012 R2, migrating to D365 F&O.

We would like a singe works order to move to different warehouses during it’s route. Whilst the current requirement doesn’t have material consumption from all operations against more than one warehouse, it could one day do so. The actual requirement is to

Backflush from warehouse A
Be tested against a later operation in warehouse B
End up in warehouse C for shipping when reported as finished (or by a planned transfer order)

We’ve been told this isn’t possible by our Partner, so getting a second opinion here for fullness.

Thanks

Is this all on a single production order?

hi Jacob, yes, ideally on a single production order