Hello all,
I have a strange occurrence at a client site where job scheduling was scheduling items for completion next year, even though it appeared that sufficient capacity was available this year and the due date was this year. I looked at the working times against the specific work centres and re-generated them, which seemed to cure the problem when I re-scheduled. My question is this:
Because work centres reference calendars which in turn have their own working time template, is it sufficient to regenerate working times at calendar level rather than for each work centre, as we have hundreds.
Cheers
Jon