Wait Time

I belive that the logic of “wait time” in the routing is wrong! if I put in 10 hours wait time and 0 run & 0 set times when the working shift is for 8 hours then the job waits for all of one shift then 2 hours of the next shift which I calculate as being a wait time of 26 hours! Wait time should be INDEPENDENT of working shifts - does everyone agree?

Hi Chris No problems argreeing with you, wait time is theoretically independent of shift time - the trick is to get navision to agree with you when you log it! [:D]