I am using Dynamics NAV 2009 R2. Here is the issue:
I make part A. (all is good with this) cost is 5.00 per unit
I then have to send part A to a sub-contractor to do something to it. That adds 2.00 per unit. It also makes it into Part B. The sub-contractor on gives me a bill for the additional amount. So when I receive Part B it show cost of only 2.00 per unit, I’ve lost the original 5.00 per unit cost.
Sort of a module, but more functionality integrated into the manufacturing module. Here you’re setting up specific work centers as sub-contractors by specifying the vendor no. for the sub-contractor. NAV will then handle the creation of purchase orders and transfer of “raw-material” to the vendor including the completion of the production order when finished.