Hi,
When I run the master planning, I got the error as below:
Job exceeds the maximum job lead time of 200 days.
I tried to change the calendar, but still no luck.
Thanks,
Hi,
When I run the master planning, I got the error as below:
Job exceeds the maximum job lead time of 200 days.
I tried to change the calendar, but still no luck.
Thanks,
I don’t think it is the calendar, look at your capacity settings for the operation, it seems that you have indicated something like 1 piece/hour and you need to produce 1000000 pieces, therefore you exceed the maximum lead time allowed for one job.