Running master planning - error

Hi,

When I run the master planning, I got the error as below:

Job exceeds the maximum job lead time of 200 days.

I tried to change the calendar, but still no luck.

Thanks,

I don’t think it is the calendar, look at your capacity settings for the operation, it seems that you have indicated something like 1 piece/hour and you need to produce 1000000 pieces, therefore you exceed the maximum lead time allowed for one job.