Released prod orders

Hi,

When i try to enter the ending date and time in released prod order then the starting date is also changed to the ending date. Is it something related to setup. I am having prob in entering the ending date when it is different from starting date whereas the system treats both the dates as same.

Sudheer

are you using a routing?

no

Routing tells Navision how long it takes to make, so if you have none then you can make and finish it at the same time.

When you do not use routes the lead time on the replenishment tab of the item card is used.