QUALITY LEAD TIME

HI,

WE ARE IN THE FINAL PHASE OF IMPLEMENTATION (DAIRY PLANT - DYAMICS 2009) AND WE ARE HAVING TROUBLE WITH THE RESULTS OF MASTER PLANING, BECAUSE THE SYSTEM IS ADDING QUALITY CONTROL TIMES (48 HRS) AS CUMULATIVE FOR EACH BATCH PRODUCED. RESULTING (FOR EXAMPLE) IN 68 DAYS OF WAITING TIME IN SOME CASES…

I ALREADY ASKED OUR PARTNER TO CHECK FOR A FIELD THAT SHOULD BE CONFIGURED TO INSTRUCT THE SYSTEM TO CONSIDER 48 HRS AS A GENERAL QUALITY ASSURANCE LEAD TIME, REGARDLESS OF THE NUMBER OF BATCHES PRODUCED IN ONE DAY, OR TO CONFIGURE QUALITY CHECK TIME IN A WORK CENTER WITH INFINITE CAPACITY,

I KNOW THIS MUST RESPOND TO SOME BASIC CONFIGURATION, BUT THEY HAVENT BEEN ABLE TO FIGURE IT OUT YET…

ANY COMMENTS?

THANKS…