Project Management & Accounting in AX 2012

Hi all,

Here i am facing a problem in Project Management & Accounting in AX 2012.

From the existing project, i want to create a subproject. (Selecting main project > Edit > Subproject, new in the action pane). But when i am clicking that subproject button an error is coming saying that “Calendar needs to be set for parent project”.

Same error is coming also when i am going to create a new Work Breakdown Structure for an existing project.

Please help me in solving the issue. Your solution is highly appreciated.

Thanks in advance)))))

Regards,

Parashar Banerjee.

Hi Parashar Banerjee,

IN the parent Project under Scheduling Tab you have scheduling calender specify the calender in the filed provided, then you can create Sub-Projects.

It worked as i wanted.

Thanks a lot Ashwin… [Y]

In the parent Project under Scheduling Tab you have scheduling calender specify the calender in the filed provided, then you can create Sub-Projects.