Hi,
Is it OK, if we change (increase) the Consumption qty on the Production Picking list and then Post it? Is this System wise OK ?
Or should it be changed in the Production BOM and then a new picking list is created
Regards
Thomas Philipose
Hi,
Is it OK, if we change (increase) the Consumption qty on the Production Picking list and then Post it? Is this System wise OK ?
Or should it be changed in the Production BOM and then a new picking list is created
Regards
Thomas Philipose
Nope that is fine, do it and have an analysis, will cause variance or increased cost of course.
System will allow you to increase / decrease quantity . To change in production formula is difficult because only at created stage you can change it .
So better to change in picking list so actual cost will come after end of production order .
You can change a started production BOM depending upon your version. However you should also re-estimate if you do, but it asks you (AX2012R2? onwards I think)
Dear Adam/Shivraj,
Thanks for the replies.
regards
Thomas Philipose