Production order use double raw material at the time of END.

AOA

I am facing an errer in AX production module

during production I am using one raw material for one finish goods,

when i create an production order and proceed it ( Estimate, Release, Start, Report as Finished) til Report as finished the production order consume single raw material But as i END the production order, the production order consume double raw material for producing one finish good.

Please highlight the problem.

i shall be thankful for your future consideration.

Do you have RAF ticked on END?

How and where do you report consumption currently?

Is the End Job selected on the picking list?