Production order No. ##### could not be scheduled. Not enough capacity

Hi everyone,

I have a route design production as below :

Oper No. Priority Operation Next Link Resource Req. Cost Category

10 Primary Process 1.1 20 Resource R1 R1-Depreciation

10 Secondary1 Process 1.2 20 Resource R1 R1-Repair

10 Secondary2 Process 1.3 20 Resource R1 R1-Labor

20 Primary Process 2.1 0 Resource R1 R1-Depreciation

20 Secondary1 Process 2.2 0 Resource R1 R1-Repair

20 Secondary2 Process 2.3 0 Resource R1 R1-Labor

I use secondary process because I have one or more cost category for each resource.

I can use this route design into job scheduling of batch order in AX 2012, but why I can’t use this route design into job scheduling of batch order in AX 2012 R2 ? this route design only running when I use operation scheduling of batch order in AX 2012 R2.

If I try to running this route into schedule job, system give me error message “Production order No. ##### could not be scheduled. Not enough capacity”.

Anyone know why this happened?

Have a read of this:

http://blogs.msdn.com/b/axmfg/archive/2013/01/24/production-order-could-not-be-scheduled-not-enough-capacity-could-be-found-how-to-get-to-the-bottom-of-this.aspx

Hi Adam roue,

Thanks for your reply,

I have checked from first point to seventh point, and it doesn’t matter. But when I try to check point 8, I have difficult to find log file name**: Program Files\Microsoft Dynamics AX\60\Server\MicrosoftDynamicsAX\Log\SchedulingDataModel_[funky_numbers_here].xml**

In my server only there are two log file name : trcAxaptaError and trcAxaptaSync.

How can I generate schedulingdatamodel.xml? Or are there some settings in system to generate this log?

Thanks for your help,

You will need to speak to your technical department. I did not write the referenced blog, that is Microsoft. Alternatively you can ask them.