Hi all,
I’m trying to understand why there is a large scheduling gap between the first operation 10 and the next operation 20 for the finished goods.
This should not be happening, as the resource group that is used for the 10 operation bears resources that have infinite capacity, so the first operation should be scheduled just in time to meet the schedule of 20 operations when backward scheduling. The clock hour queue used is only 24 between operations so this shouldn’t be the cause.
This is the actual route that the system gives:
Op.No Task type Res. No Start Date start time End date End time
10 Process Resource 1 02/24/2014 06:45am 2/14/2014 06:49 am
10 Queue after Resource1 2/14/2014 06:49 am 2/15/2014 06:49 am
20 Setup Resource 2 2/24/2014 01:53 pm 2/24/2014 02:42 pm
…
70 process Resource 4 2/25/2014 04:59 pm 2/25/2014 05:04 pm
Any help will be appreciated on that .