Hi, we are using Dynamics AX 2009 and having a hard time understanding how AX determines the requirement dates of some production batch orders after regeneration. We have finite capacity turned off. Here is a scenario:
Current Date = Jan 15
ITEM1 has item coverage period = 21 days with Issue margin=0, no safety margin, no on hand quantity, no forecast
Demand for the coverage period = 1000 units or a sales order for 200 units each day from Jan 20 - 24 (5 SO’s total)
Item max order quantity = 500
When I run regeneration on Jan 15, shouldn’t I expect to see 2 planned batch orders with Jan 15 requirement date for 500 each?
I am somewhat of a novice so let me know if you need more information that what is above.
Thanks for the help!
-Jeff
The second one for 500 would theoretically be being made 2 days early as you do not need it until the 17th - that should be the requirement date - because of your maximum quantity creating the second order which means the coverage period of 21 days is essentially reset. However that is how I would interpret it - what AX does is another matter altogether - what is it doing with that setup? I am assuming your routing is 5 days because if you had no routing and all component stock on hand then the first requirement day would be the 20th, not the 15th.
Thanks for the answer. What’s happening now in this scenario is that pretty much what you’re indicating - a planned batch order is created a day or 2 before the SO requirement date. What do you mean by “the coverage period of 21 days is essentially reset”? I am not sure what routing is set to. I will check on that.
If instead of SO demand I had a sales forecast on Jan 20 for 1000, what requirement dates should I expect to have?
Thanks again, this helps a lot.
Jeff
Well logically the 21 day period is not 21 from Jan 15, it is 21 from the demand, and when the order is fulfilled it looks forward for the next demand - your restriction is the 500, so therefore the 21 is reset as it looks for new demand. It is a moving bucket, not a fixed 21 days.
If you had 1000 on Jan 20 and NO sales orders I would expect the requirement date of the 2 orders to be the 20th, although you have default receipt times in the parameters which can add a day lag depending upon the set and then you have the margin days on the coverage group and on the plan which are cumulative.
If you had 4 elements of demand on 20, 21, 22 and 23 I would not expect it 2 days before it was required, but instead one with a requirement of the 20 to meet 20 and 21 with the max and the second on the 22. However with the routing, default receipt and pick times, transport days, safety margins etc there are lots of ways to see additional days sneak in but the requirement date will still essentially be the same, it is the order date that moves backwards in time.
This is great information and really helps to understand some of the factors involved. I think it will help to create several tightly controlled test scenarios.
Many thanks!