Hi All,
Please give your comments on following scenario
Scenario: - Finish good item A
Item |
Status |
BOM no |
Route no |
SKU exsit |
---|---|---|---|---|
A |
Finish good |
BOM-A |
Route-A |
Yes.( WIP–>production) FG-store–>transfer from WIP) |
B |
BOM item of A |
BOM-B |
Route-B |
Yes(WIP–>Production) |
C |
BOM of item B |
BOM-C |
Route-C |
Yes(WIP–>Production) |
D |
BOM of item C |
BOM-D |
Route-C |
Yes (WIP–>Production) |
Released Sales order with 100 Qty. of item A. (order date & shipment date equal to 18/09/2013)
-
Run planning worksheet (PW) with the start date equal to (18/09/2013)
-
Result;
Item No |
Due date |
Start date & time |
End date & time |
Order No |
---|---|---|---|---|
A |
09/18/13 |
09/17/13 11:39:57.997 PM |
09/18/13 07:59:59 AM |
Order No 1 |
B |
09/17/13 |
09/14/13 05:28:55.997 PM |
09/17/13 07:59:59 AM |
Order No 2 |
C |
09/17/13 |
09/16/13 04:29:57.997 PM |
09/17/13 07:59:59 AM |
Order No 3 |
D |
09/17/13 |
09/16/13 06:59:57.997 AM |
09/17/13 07:59:59 AM |
Order No 4 |
· Normal starting time 8.00.00 AM (Manufacturing setup)
· Normal End time 7.59.59 AM (Manufacturing setup)
· Company run three work shift (8 hours for each)
-
Here you can see PW it was calculated backward. Can’t we set it as forward calculation? (When run PW)
-
Here I want to start the process & end the process sequentially. As an example,
a. Order no 4(item D) has to start first & after it finish only order No 3 (Item C) can start.
b. Then order No 2 (Item B) can start & after it finish only Order No1 ( item A) should plan
Sample plan.
Item No |
Due date |
Start date & time |
End date & time |
Order No |
---|---|---|---|---|
A |
09/18/13 |
09/17/13 16.00 PM |
09/18/13 07:59:59 AM |
Order No 1 |
B |
09/17/13 |
09/17/13 13.00 PM |
09/17/13 16.00 PM |
Order No 2 |
C |
09/17/13 |
09/17/13 10.00AM |
09/17/13 13.00 PM |
Order No 3 |
D |
09/17/13 |
09/16/13 7.00 PM |
09/17/13 10.00 AM |
Order No 4 |
Is there are any standard function to this scenario? Currently we customized.