Partial Production Order

Hi All,

In AX 2012, Can any one give me suggations for executing Partial Production from single Production Order.

Example :

Production Order : 5000 Nos

Day 1 : 1000 Nos started and report as finished

Day 2 : 1000 Nos started and report as finished

Day 3 : 3000 Nos started and report as finished

How to resolve mention above problem in AX 2012…

Regards,

Parth

Report as Finished the actual quantity and do not tick the “End Job” flag until the last receipt.

Thanx Adam…

Regards,

Parth

Thanx Adam…

Regards,

Parth