Order of pos in BOM

Hi, is there a difference, if I enter in the first position of a BOM the last material needed in the production of goods, or have I to enter the first material, which goes into the process in the first position. The same regarding the operation no. in routings. Have I to enter the first Work center, with which the production starts, than the second and so on. Many thanks Michael

Hi Michael, Use “Routing Link Codes” to specify which material should go at what operation … In ideal case it is always better to specify the Operations in a sequence. Regards, Srinivas Shetty