# Operations scheduling - Job scheduling

**URL:** <https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183>\
**Category:** User Forum\
**Created:** [December 11, 2012, 7:24am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183 "2012-12-11T07:24:43Z")\
**Posts on this page:** 7\
**Page:** 1

<div class="post-metadata">

**Author:** ![prasadgvr](https://avatars.discourse-cdn.com/v4/letter/p/dc4da7/32.png) [@prasadgvr](https://www.dynamicsuser.net/u/prasadgvr)\
**Post date:** [December 11, 2012, 7:24am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/1 "2012-12-11T07:24:43Z")

</div>

For a selected item in AX 2012 whenever i perform operations scheduling and exception is thrown indicating “Production order could not be scheduled. Not enough capacity could be found”.

But for same item/production order Job scheduling is working absolutely fine.

Any thoughts???

---

<div class="post-metadata">

**Author:** ![erp.psarathy](https://avatars.discourse-cdn.com/v4/letter/e/47e85d/32.png) [@erp.psarathy](https://www.dynamicsuser.net/u/erp.psarathy)\
**Post date:** [December 11, 2012, 8:33am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/2 "2012-12-11T08:33:03Z")

</div>

Hi Prasad,

Check the Inventory of BOM and Items. I think it does not enough inventory on-hand.

Sarathy

---

<div class="post-metadata">

**Author:** ![prasadgvr](https://avatars.discourse-cdn.com/v4/letter/p/dc4da7/32.png) [@prasadgvr](https://www.dynamicsuser.net/u/prasadgvr)\
**Post date:** [December 11, 2012, 8:41am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/3 "2012-12-11T08:41:09Z")

</div>

Hi Sarathy,

Thank you for the reply. Logically speaking system must allow the user for scheduling the production order although material is not available on-hand and this can be done by not specifying “finite Material”.

Not having on-hand inventory, if it stops operations scheduling, it should restrict job scheduling as well.

---

<div class="post-metadata">

**Author:** ![AdamRoue](https://avatars.discourse-cdn.com/v4/letter/a/c37758/32.png) [@AdamRoue](https://www.dynamicsuser.net/u/AdamRoue)\
**Post date:** [December 11, 2012, 9:23am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/4 "2012-12-11T09:23:39Z")

</div>

Ensure when you schedule on the tabs you do not have finite material or capacity ticked, then if you have a bottleneck item in the route check the calendar.

---

<div class="post-metadata">

**Author:** ![prasadgvr](https://avatars.discourse-cdn.com/v4/letter/p/dc4da7/32.png) [@prasadgvr](https://www.dynamicsuser.net/u/prasadgvr)\
**Post date:** [December 11, 2012, 10:36am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/5 "2012-12-11T10:36:59Z")

</div>

Both finite Material and Finite capacity are unchecked while scheduling and none of the resources are created as Bottleneck resources or exclusive resources.

still the problem persists…[:(]

---

<div class="post-metadata">

**Author:** ![prasadgvr](https://avatars.discourse-cdn.com/v4/letter/p/dc4da7/32.png) [@prasadgvr](https://www.dynamicsuser.net/u/prasadgvr)\
**Post date:** [December 11, 2012, 10:39am UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/6 "2012-12-11T10:39:00Z")

</div>

My Operation requires only 4 hrs, Calendar is set to 8 hrs per day from 9am to 1pm and 2pm to 6pm. only one calendar…

---

<div class="post-metadata">

**Author:** ![AdamRoue](https://avatars.discourse-cdn.com/v4/letter/a/c37758/32.png) [@AdamRoue](https://www.dynamicsuser.net/u/AdamRoue)\
**Post date:** [December 11, 2012, 6:22pm UTC](https://www.dynamicsuser.net/t/operations-scheduling-job-scheduling/42183/7 "2012-12-11T18:22:20Z")

</div>

Can you post your routing and work centre settings?