One Route produces four different BOM simultaneously

Hi AXperts!!!

I need your help and opinions on how to set-up 1 route which will produce four different BOMs (with its own distinct BOM numbers) simultaneously? In one of our process called injection we produce 4 different WIP Parts (BOM) at the same time with one Raw Material.

Thanks.

I would use the Process Manufacturing elements and create by-products. However the BOM number is irrelevant here, it would book in stock of a BOM type item. If it is a true WIP part it arguably does not matter, so you probably need to explain your actual requirements in more detail.

Where and how can I set this up? Can you enlighten me with this one?

Thanks and best regards.

Well first you need to have purchased these modules - have you?