Hello,
I am not sure about what exactly does the net change planning method.
I will explain what is doing to us:
I have a planned production order of 100000 Z and I have 50000 A items on the warehouse to manufacture it. So if I execute the planning with net change it suggests me to purchase 50000 A. It works fine so far.
Now, I delete 50000 A of my warehouse with a recount (without having received the other 50000) and execute again the planning on net change. It suggests a purchase order of 100000 A. Still working fine.
Then, and here is the problem, if I add 50000 A on the warehouse with a recount and execute again the planning on net change it does not delete the purchase order of 100000 so now, on my net requirements I have 50000 A on-hand and a purchase order of 100000 A (so I would have 150000 on-hand on the future).
My question is: Shouldn’t it adjust the quantity on the purchase order in order to buy just 50000 A items? So I would have 50000 on the warehouse and 50000 ordered.
We understand that there is no sense on those variations on the quantity of items, but this is just a test to understand why net change does not adjust the purchase orders or just deletes them.
Thank you.