Hi All,
Client wants to use the planning worksheet.
Problem is on the calculate regenerative plan.
Here’s the scenario:
SKU CARD
Location: Blue
Reordering Policy=Lot for Lot
Leadtime Calculation: 60 days
Safety stock=120
Inventory on Hand: 80
PRODUCTION FORECAST
Location: Blue
Forecast: January 2014 = 90, February = 110, March = 120
WORK DATE= 1/1/14
When i run the calculate regenerative plan,
it shows the following:
Warning Order Date Due Date Quantity
Exception 11/2/13 1/1/14 130
New 12/3/13 2/1/14 110
New 12/31/13 3/1/14 120
If planning date = 1/1/14 or the work date, why would the system display order dates of 11/2, 12/3, 12/31 which are obviously no longer possible. Is there a setup that will say, given your situation, start order today, 1/1/14, so that it becomes due on these future date xxx (using the lead time).
Thanks in advance